A copy, not the official record, and not a finding. An odd pattern is a question, never proof. Purchase orders count from 2026-06-01. Read this in full before using the Docket
This is VI Update's cleaned-up copy of what the Government of the Virgin Islands publishes on GVIBuy and in its checkbook; confirm anything that matters on those official systems. Government purchasing is complicated, and a pattern that looks odd usually has an ordinary explanation: it is a question to ask, never proof of wrongdoing on its own. Read this first.What these analyses cover, and from when they hold. Purchase orders: complete only from 2026-06-01, when GVIBuy took over agency purchasing (no older order was moved in, so earlier years hold only contracts and a few orders). Bids: from 2022-02-28, but complete only from our first read of GVIBuy's lists on 2026-09-02; anything removed before then is missing, so earlier counts are a floor. Payments: the checkbook from 2022-10-03 (fiscal 2023). Every figure is as of the histories read 2026-11-21 and the checkbook statuses of 2026-11-20. Compare years only where both are covered.
Lucas Pascal
108 steps on 29 documents, 2026-06-25 to 2026-10-14. A GVI account acting in its public role, as GVIBuy prints it. GVIBuy credits a step to the account that recorded it; it does not say who decided.
Steps by status
| 2BS Sent | 20 |
| 2BRA Ready for Approval | 20 |
| 2BR Ready to Send | 20 |
| 2BI In Progress | 20 |
| 2BE Evaluated | 15 |
| 3PCR Complete Receipt | 9 |
| 2BIA Intent To Award | 2 |
| 2BO Opened | 1 |
| 2BC Canceled | 1 |
Documents by department
| Bid, department not yet read | 20 |
| Office of the Virgin Islands Inspector | 9 |
Credited with every step of a document, beside the usual pattern
| Kind | This account's documents | Every step credited to one account | The same, across all accounts |
|---|---|---|---|
| Open Market Bid | 20 | 1 (5.0%) | 565 of 2,570 (22.0%) |
| Open Market Purchase Order | 9 | 0 (0.0%) | 34 of 967 (3.5%) |
Documents with more than one step. "Every step credited to one account" counts this account's documents whose whole history is credited to it alone. Some kinds (payment authorizations especially) are often handled by one account start to finish, so read each row against the right-hand column, which is the same figure for every account.
When this account's steps were recorded
Outside 7 a.m. to 6 p.m. or on a weekend: 10 of 108 steps (9.3%); across every account, 14.3%. Some kinds of document are processed in evening batches; see Patterns.
Latest steps (100 of 108)
| When (AST) | Status | Document |
|---|---|---|
| 2026-10-14 09:48 | 2BS Sent | BD-27-350-3502-3555 Ethernet Network Cable Installation STX |
| 2026-10-14 09:48 | 2BR Ready to Send | BD-27-350-3502-3555 Ethernet Network Cable Installation STX |
| 2026-10-14 09:48 | 2BRA Ready for Approval | BD-27-350-3502-3555 Ethernet Network Cable Installation STX |
| 2026-10-14 09:40 | 2BI In Progress | BD-27-350-3502-3555 Ethernet Network Cable Installation STX |
| 2026-10-14 09:39 | 2BS Sent | BD-27-350-3501-3554 Ethernet Network Cable Installation STT |
| 2026-10-14 09:35 | 2BR Ready to Send | BD-27-350-3501-3554 Ethernet Network Cable Installation STT |
| 2026-10-14 09:35 | 2BRA Ready for Approval | BD-27-350-3501-3554 Ethernet Network Cable Installation STT |
| 2026-10-14 09:22 | 2BI In Progress | BD-27-350-3501-3554 Ethernet Network Cable Installation STT |
| 2026-10-14 09:20 | 2BS Sent | BD-27-350-3501-3551 2021 Honda Passport Servicing |
| 2026-10-14 09:19 | 2BR Ready to Send | BD-27-350-3501-3551 2021 Honda Passport Servicing |
| 2026-10-14 09:19 | 2BRA Ready for Approval | BD-27-350-3501-3551 2021 Honda Passport Servicing |
| 2026-10-14 09:00 | 2BI In Progress | BD-27-350-3501-3551 2021 Honda Passport Servicing |
| 2026-10-01 11:59 | 3PCR Complete Receipt | PO-26-350-3501-1840 Coupons for 5 Gal. Water |
| 2026-09-30 12:50 | 2BE Evaluated | BD-26-350-3501-2491 Purchase of Chevy Equinox Black |
| 2026-09-28 12:24 | 3PCR Complete Receipt | PO-26-350-3501-1577 Paint Exterior of Office Building |
| 2026-09-23 15:49 | 3PCR Complete Receipt | PO-26-350-3501-1876 Upgrade Lighting on Second Floor Main Office |
| 2026-09-18 17:47 | 2BE Evaluated | BD-26-350-3501-2488 Copiers |
| 2026-09-09 19:22 | 2BC Canceled | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-09-09 19:16 | 2BS Sent | BD-26-350-3501-2558 Installation of Faucets |
| 2026-09-09 19:16 | 2BR Ready to Send | BD-26-350-3501-2558 Installation of Faucets |
| 2026-09-09 19:16 | 2BRA Ready for Approval | BD-26-350-3501-2558 Installation of Faucets |
| 2026-09-09 19:11 | 2BI In Progress | BD-26-350-3501-2558 Installation of Faucets |
| 2026-09-08 13:24 | 2BS Sent | BD-26-350-3501-2491 Purchase of Chevy Equinox Black |
| 2026-09-08 13:24 | 2BR Ready to Send | BD-26-350-3501-2491 Purchase of Chevy Equinox Black |
| 2026-09-08 13:24 | 2BRA Ready for Approval | BD-26-350-3501-2491 Purchase of Chevy Equinox Black |
| 2026-09-08 13:08 | 2BI In Progress | BD-26-350-3501-2491 Purchase of Chevy Equinox Black |
| 2026-09-08 12:43 | 2BS Sent | BD-26-350-3501-2488 Copiers |
| 2026-09-08 12:25 | 2BR Ready to Send | BD-26-350-3501-2488 Copiers |
| 2026-09-08 12:25 | 2BRA Ready for Approval | BD-26-350-3501-2488 Copiers |
| 2026-09-08 12:10 | 2BI In Progress | BD-26-350-3501-2488 Copiers |
| 2026-09-02 09:52 | 2BE Evaluated | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-09-01 18:51 | 2BE Evaluated | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-09-01 07:35 | 3PCR Complete Receipt | PO-26-350-3501-1808 Supplies |
| 2026-08-31 10:40 | 2BE Evaluated | BD-26-350-3501-2021 Coupons for 5 Gal. Water |
| 2026-08-27 11:56 | 3PCR Complete Receipt | PO-26-350-3501-1777 Main Office Supplies |
| 2026-08-26 13:11 | 2BE Evaluated | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-26 13:08 | 2BE Evaluated | BD-26-350-3501-2025 Supplies |
| 2026-08-25 14:55 | 2BS Sent | BD-26-350-3501-2025 Supplies |
| 2026-08-25 14:55 | 2BR Ready to Send | BD-26-350-3501-2025 Supplies |
| 2026-08-25 14:55 | 2BRA Ready for Approval | BD-26-350-3501-2025 Supplies |
| 2026-08-25 14:39 | 2BI In Progress | BD-26-350-3501-2025 Supplies |
| 2026-08-25 14:28 | 2BS Sent | BD-26-350-3501-2021 Coupons for 5 Gal. Water |
| 2026-08-25 14:27 | 2BR Ready to Send | BD-26-350-3501-2021 Coupons for 5 Gal. Water |
| 2026-08-25 14:27 | 2BRA Ready for Approval | BD-26-350-3501-2021 Coupons for 5 Gal. Water |
| 2026-08-25 14:12 | 2BI In Progress | BD-26-350-3501-2021 Coupons for 5 Gal. Water |
| 2026-08-25 13:58 | 2BE Evaluated | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-08-25 13:35 | 2BE Evaluated | BD-26-350-3501-1984 Main Office Supplies |
| 2026-08-25 13:00 | 2BE Evaluated | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-24 17:21 | 2BS Sent | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-24 17:20 | 2BR Ready to Send | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-24 17:20 | 2BRA Ready for Approval | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-24 17:01 | 2BI In Progress | BD-26-350-3501-1994 Upgrade Lighting on Second Floor Main Office |
| 2026-08-24 15:20 | 2BS Sent | BD-26-350-3501-1984 Main Office Supplies |
| 2026-08-24 15:20 | 2BR Ready to Send | BD-26-350-3501-1984 Main Office Supplies |
| 2026-08-24 15:20 | 2BRA Ready for Approval | BD-26-350-3501-1984 Main Office Supplies |
| 2026-08-24 14:11 | 2BI In Progress | BD-26-350-3501-1984 Main Office Supplies |
| 2026-08-24 13:01 | 3PCR Complete Receipt | PO-26-350-3501-1588 Upgrade Lighting on First Floor |
| 2026-08-20 18:19 | 2BE Evaluated | BD-26-350-3501-1724 IT Equipment |
| 2026-08-18 09:14 | 2BS Sent | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-08-18 09:14 | 2BR Ready to Send | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-08-18 09:14 | 2BRA Ready for Approval | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-08-18 08:22 | 2BI In Progress | BD-26-350-3501-1817 Upper Deck Repairs |
| 2026-08-17 09:46 | 3PCR Complete Receipt | PO-26-350-3501-1616 Replacement Door Frames |
| 2026-08-15 10:56 | 2BS Sent | BD-26-350-3501-1727 Purchase of White Chevy Equinox |
| 2026-08-15 10:56 | 2BR Ready to Send | BD-26-350-3501-1727 Purchase of White Chevy Equinox |
| 2026-08-15 10:56 | 2BRA Ready for Approval | BD-26-350-3501-1727 Purchase of White Chevy Equinox |
| 2026-08-14 12:01 | 3PCR Complete Receipt | PO-26-350-3501-1619 Purchase Of Bulk Tickets VIIG |
| 2026-08-14 11:43 | 3PCR Complete Receipt | PO-26-350-3501-1547 Magnetic Security Lock on Back Door |
| 2026-08-12 15:56 | 2BI In Progress | BD-26-350-3501-1727 Purchase of White Chevy Equinox |
| 2026-08-12 14:57 | 2BS Sent | BD-26-350-3501-1724 IT Equipment |
| 2026-08-12 14:57 | 2BR Ready to Send | BD-26-350-3501-1724 IT Equipment |
| 2026-08-12 14:57 | 2BRA Ready for Approval | BD-26-350-3501-1724 IT Equipment |
| 2026-08-12 14:36 | 2BI In Progress | BD-26-350-3501-1724 IT Equipment |
| 2026-08-12 12:19 | 2BS Sent | BD-26-350-3501-1711 Office Supplies |
| 2026-08-12 12:19 | 2BR Ready to Send | BD-26-350-3501-1711 Office Supplies |
| 2026-08-12 12:19 | 2BRA Ready for Approval | BD-26-350-3501-1711 Office Supplies |
| 2026-08-12 12:04 | 2BI In Progress | BD-26-350-3501-1711 Office Supplies |
| 2026-07-27 08:36 | 2BE Evaluated | BD-26-350-3501-1215 Purchase Of Bulk Tickets VIIG |
| 2026-07-24 11:28 | 2BS Sent | BD-26-350-3501-1317 Replacement Door Frames |
| 2026-07-24 11:28 | 2BRA Ready for Approval | BD-26-350-3501-1317 Replacement Door Frames |
| 2026-07-24 11:28 | 2BR Ready to Send | BD-26-350-3501-1317 Replacement Door Frames |
| 2026-07-24 11:16 | 2BI In Progress | BD-26-350-3501-1317 Replacement Door Frames |
| 2026-07-21 14:21 | 2BIA Intent To Award | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-21 08:37 | 2BE Evaluated | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-20 15:24 | 2BE Evaluated | BD-26-350-3501-992 Paint Exterior of Office Building |
| 2026-07-20 11:07 | 2BS Sent | BD-26-350-3501-1215 Purchase Of Bulk Tickets VIIG |
| 2026-07-20 11:06 | 2BR Ready to Send | BD-26-350-3501-1215 Purchase Of Bulk Tickets VIIG |
| 2026-07-20 11:06 | 2BRA Ready for Approval | BD-26-350-3501-1215 Purchase Of Bulk Tickets VIIG |
| 2026-07-20 10:58 | 2BI In Progress | BD-26-350-3501-1215 Purchase Of Bulk Tickets VIIG |
| 2026-07-20 10:35 | 2BIA Intent To Award | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-09 14:37 | 2BS Sent | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-09 14:37 | 2BR Ready to Send | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-09 14:37 | 2BRA Ready for Approval | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-09 11:54 | 2BI In Progress | BD-26-350-3501-1039 Purchase of Chevy Equinox |
| 2026-07-07 07:35 | 2BE Evaluated | BD-26-350-3501-822 Magnetic Security Lock on Back Door |
| 2026-07-06 16:48 | 2BO Opened | BD-26-350-3501-822 Magnetic Security Lock on Back Door |
| 2026-07-06 16:08 | 2BS Sent | BD-26-350-3501-992 Paint Exterior of Office Building |
| 2026-07-06 16:01 | 2BR Ready to Send | BD-26-350-3501-992 Paint Exterior of Office Building |
| 2026-07-06 16:01 | 2BRA Ready for Approval | BD-26-350-3501-992 Paint Exterior of Office Building |
| 2026-07-06 13:53 | 2BI In Progress | BD-26-350-3501-992 Paint Exterior of Office Building |
Every step credited to this account, as a spreadsheet: download the CSV.
What was last refreshed when, and how often
| Data | Last refreshed | How often |
|---|---|---|
| GVIBuy's purchase-order list (new documents, list statuses, what has left the list) | 2026-11-18 14:53 UTC | weekly, Wednesdays |
| GVIBuy's bid list (new documents, list statuses, what has left the list) | 2026-11-18 14:56 UTC | weekly, Wednesdays |
| GVIBuy's blanket list (expired included) (new documents, list statuses, what has left the list) | 2026-11-19 00:46 UTC | weekly, Wednesdays |
| Status histories (purchase orders) | 2026-11-21 10:00 UTC | daily windows for new and changed documents; a monthly sweep of unfinished ones |
| Status histories (bids) | 2026-11-21 10:08 UTC | daily windows for new and changed documents; a monthly sweep of unfinished ones |
| Vendor profiles | 2026-11-21 03:15 UTC | daily windows for new and changed vendors; every profile quarterly |
| Purchase-order and blanket detail pages (dollar limits, entered dates, vendor IDs) | 2026-11-19 | weekly 2,480 read 2026-11-19; 30 read 2026-09-03; 1,881 read 2026-09-02 |
| Name ties between GVIBuy and the checkbook | 2026-11-21 02:36 UTC | twice a day, after each warehouse refresh (06:10 and 18:30 AST) |
| Checkbook payments (Paid and Approved statuses, by fiscal year) | 2026-11-20 | twice a day FY2023–FY2025 read 2026-11-11; FY2026 read 2026-11-17; FY2027 read 2026-11-20 |
| This page (the Ledger's copy) | rebuilt from the above | nightly |
Each date is read from the table that holds that data. GVIBuy is the Government of the Virgin Islands' procurement site (gvibuy.buyspeed.com); its agency purchase-order record begins 2026-06-01, while the territorial checkbook's begins in fiscal 2023. A document's current state can have moved on GVIBuy since it was read here.
Times are Atlantic Standard Time (UTC−4), on a clock calibrated 2026-11-20: GVIBuy prints AST from 17 October 2022 and four hours early before 14 October 2022, and those earlier steps are corrected here. GVIBuy credits each step to the account that recorded it; that is not always the person who decided. The names are GVI staff acting in their public role, as GVIBuy prints them. Everything here is public on GVIBuy or in the checkbook; this page gathers it.